Piping Project, North East

Description

Addison Engineering were engaged by our client to upgrade their existing plant in to increase production capacity from 2,000 to 3,000 tonnes per year.

A fast track, cut and carve project, this required close involvement with both the client project team and the principal contractor  and required precise planning to complete with minimum disruption to production.

Gallery

Project Scope

Our role as Mechanical Contractor involved the fabrication and assembly of pipe work and installation of main plant equipment.

"I’d just like to let you know how impressed I’ve been with the way your engineers have worked together with us on this project." High Performance Plastics Producer